I have recently gotten a question and do hope that I would be able to receive some aid in solving it:
-----------------------------------
Create SOP (Oct, Nov, Dec) for (20,10,30) and run MRP to generate the plan orders.
There is an urgent sales order of 10 units coming in soon. There is a need to do a build of 10 units in June (Assuming the current period is June). What do you do in the perspective of a planner?
Eventually, the sales order is not accepted.
Planner manually creates a plan order for 15 Nov of 5 units.
Rerun MRP.
Explains what happens.
---------------------------------